OdinTask field-service app OdinTask ODINTASK · GUIDE
groundworks

Utility Search and Excavation Records for Groundworks

10 July 2026 · 9 min · groundworksexcavationdocumentationsite safetyledningskollen

Utility search and excavation records for groundworks come down to four things done in order: submit a utility search before you price the programme, get a marking-out on the ground (in Sweden a ledningsanvisning, requested free through Ledningskollen.se, allowing at least five working days), hand-dig inside the protected zone either side of every marked line, and photograph the open trench before you backfill. The photographs are the part most firms skip and the only part that matters once a network owner sends a damage claim. A timestamped, located set of pre-backfill images showing the marks, the hand-dug approaches, measured depths and undamaged ducts answers the claim before it is made. Without them you are arguing your memory against their repair invoice.

Why this got harder by 2026

The ground is more crowded than it was five years ago. Fibre pushed shallow ducts down thousands of verges and driveways, some micro-trenched far shallower than older crews expect. District heating expanded through the same streets. EV charge points added low-voltage runs to car parks, kerbsides and domestic driveways, often installed quickly and recorded by nobody. More strikes per metre dug, and a patchier record of what is down there. A drawing showing one cable in a verge is not a promise there is only one. The contractor who assumes the drawing is complete pays. The one with a pre-backfill photo set does not.

What a utility search actually is, and what it is not

In Sweden, Ledningskollen.se is a free national service run by PTS, the post and telecom authority. You draw your dig area on a map, say what you are doing and when, and the service forwards the request to every network owner registered for that area. Each owner answers independently, with one of three things:

Two request types matter most. Projektering is for the design and tender stage, when you want to know what is there before you price the work. Ledningsanvisning is for when you are about to dig. They are not interchangeable, and a projektering reply is not a licence to dig.

What it is not is complete. It only reaches owners who have registered. Private assets almost never appear: the client's supply to a garage, garden lighting, an irrigation main, a septic run, an old feed to a barn. Those are the client's to declare. Ask in writing, keep the answer. No assets from every registered owner does not mean the ground is empty.

Lead times: the number that decides your programme

The paperwork is fast. The physical marking is not. Plan backwards from the dig date.

StepRealistic allowanceNotes
Submitting the requestAbout 15 minutesFree. You need the dig polygon and your dates.
Drawings back from ownersOften 1 to 3 working daysEach owner sets its own turnaround.
Marking out on the groundCommonly 5 to 10 working daysSome owners charge for urgent or repeat attendance.
Validity of a markingOften around a monthOwner-specific, stated in the reply. If the job slips, re-request.
Sensible programme bufferTwo weeksAbsorbs one no-show without moving the client's date.

The practical rule: submit the request the day the job is confirmed, not the week you are due on site. It costs nothing and expires harmlessly. Waiting costs you a machine day and a crew.

Reading the drawings on site

Drawings arrive as PDFs with a legend, a scale and a stated tolerance. Read all three before you look at the lines.

Take the drawing to the trench, not the office wall. The person cutting the ground needs the current sheet, the case number and the marking date in their hand.

Hand-dig zones: the rule that keeps you out of court

Every network owner attaches conditions to a marking, and hand-digging is the one that is always there. The width varies: commonly no mechanical excavation within 0.5 to 1 metre either side of a marked line, wider for high-voltage and transmission assets, wider again where the stated tolerance is poor. Read each owner's terms and follow the strictest one that touches your dig. What that means in practice:

Photograph the trench before backfill

Once you backfill, the evidence is gone and the argument becomes symmetrical: they have a damaged cable and a repair invoice, you have a recollection. Every photo taken before backfill turns that into an asymmetry in your favour. The pre-backfill set, per trench section:

  1. The marks, before you dig. A wide shot of the sprayed lines against a fixed reference: kerb, corner, building line. This proves a marking existed and where it ran.
  2. The open trench, wide. The whole section from both ends, showing the relationship between the marks and the dig.
  3. Every exposed asset, close. Duct, cable, pipe, warning tape, with a tape measure or graduated rod in frame giving depth and offset. One clear shot per asset, undamaged and in focus.
  4. The hand-dug approaches. Show the zone was hand-dug. This is the shot that rebuts negligence.
  5. Bedding and surround before cover. Sand bed, tape or tiles laid, the asset intact under your work.
  6. Anything you found that was not on a drawing. Photograph it, log it, and notify the client and the owner in writing the same day. An unrecorded asset is a liability you can hand back only if you documented it.

Every image needs three properties or it is worth much less: a timestamp nobody typed, a location, and an unbroken link to the job. A folder of photos on a lad's personal phone has none of those reliably, and he leaves in March.

The excavation record that answers the claim before it is made

A damage claim asks three questions in substance. Did you request a marking? Did you follow its conditions? Did you cause the damage? Build a record whose structure answers all three without you reconstructing anything a year later.

This is a self-inspection protocol, no different in shape from an electrical egenkontroll, which is why it belongs in the same system as the job rather than a shared drive named GROUNDWORKS FINAL v2. In OdinTask you build it once as a protocol template, attach it to every groundworks job, and let the crew fill it on the field app, which works with no signal and queues the photos until there is coverage. When the claim arrives eleven months later, the case number, the marking date and the pre-backfill images are still attached to the job that produced them.

If you hit something anyway

Assume it is live. Stop, move people back, do not touch the cable and do not lean in for a closer look. Call the network owner's emergency number, then the client. Do not backfill and do not tidy. Photograph the strike exactly as it happened, including the marks, the depth and the position relative to them, before anyone repairs anything: the moment the repair crew arrives, the evidence of where that cable actually sat becomes their spoil heap. Report it the same day in writing. A strike you reported honestly with photographs is a cost. A strike you buried is a different category of problem.

Outside Sweden

The workflow transfers, the phone numbers change. In the UK, LSBUD covers many asset owners but not all, so you still contact DNOs and Openreach directly, and HSE's HSG47, Avoiding danger from underground services, is what any investigation will measure you against. New Zealand has beforeUdig, Australia has Before You Dig Australia. In every one of them the same three failures recur: the search was never made, the search was made and its conditions ignored, or the work was done properly and never photographed. The third is the cheapest to fix and it decides who pays.

If your groundworks records live across three phones and a glovebox, fix that before the next claim rather than after it. Start a free trial and build the excavation protocol once.

FAQ

How long does a ledningsanvisning take?

Plan on two weeks from request to machine. Drawings often come back within one to three working days, but physical marking on the ground commonly takes five to ten, and every network owner sets its own turnaround. The request through Ledningskollen.se is free and takes about fifteen minutes, so submit it the day the job is confirmed rather than the week you are due on site.

Is a utility search a complete record of what is underground?

No. It reaches network owners who have registered for that area, so it misses private assets almost entirely: the client's own supply to a garage, garden lighting, irrigation mains, septic runs, old feeds to outbuildings. A reply of no assets from every registered owner does not mean the ground is empty. Ask the client in writing what private services exist and keep their answer with the job record.

How far from a marked cable do I have to hand-dig?

It depends on the owner and it is stated in their reply, but commonly no mechanical excavation within 0.5 to 1 metre either side of a marked line, and wider for high-voltage and transmission assets. The marking also carries a stated tolerance, and that tolerance is part of the zone rather than separate from it. Read each owner's conditions and apply the strictest one that touches your dig.

What photographs do I need before backfilling a trench?

The marks against a fixed reference before digging, the open trench wide from both ends, every exposed duct or cable close up with a measure in frame showing depth and offset, the hand-dug approaches, the bedding and surround before cover, and anything you found that was not on a drawing. Each image needs an automatic timestamp, a location, and an unbroken link to the job record.

What do I do if I strike a cable?

Assume it is live. Stop work, move people back, do not touch it or inspect the damage closely. Call the network owner's emergency number, then the client. Do not backfill and do not tidy. Photograph the strike as it happened, including the marks and the measured depth and position, before the repair crew disturbs the evidence. Report it in writing the same day.

Is there an equivalent to Ledningskollen outside Sweden?

Yes, with the same shape and different coverage. The UK has LSBUD, which does not reach every asset owner, so you still contact DNOs and Openreach directly, and HSE's HSG47 is the guidance an investigation will judge you against. New Zealand has beforeUdig, Australia has Before You Dig Australia. In all of them the marking conditions and the pre-backfill photographs decide who pays.

One system for your field-service business

Booking, quotes with ROT, scheduling, an offline app, time tracking and invoicing — in your own brand.

Try OdinTask free