OdinTask field-service app OdinTask ODINTASK · GUIDE
contracts

Standard Construction Contracts: AB 04, ABT 06 and AB-U 07

9 July 2026 · 10 min · contractsAB 04ABT 06subcontractingÄTA

Standard construction contracts in Sweden mean three documents in particular: AB 04 for build-only work where the client owns the design, ABT 06 for design-and-build where you own the design and the function, and AB-U 07, which pushes the main contractor's AB 04 obligations down onto you as a subcontractor. Before you sign one, you need to know four things: which of the two liability models you are in, that an ÄTA (variation) claim dies if you do not notify in the required form and time, that delay is priced as vite (liquidated damages) per started week, and that your defects exposure runs as a five-year garantitid inside a ten-year ansvarstid. Everything below is the detail a one-to-twenty-person firm actually needs.

What AB 04, ABT 06 and AB-U 07 are (and are not)

They are not legislation. Sweden has no construction contracts act for commercial work. These are agreed documents, negotiated between client-side and contractor-side industry bodies and published by BKK (Byggandets Kontraktskommitté). Because both sides wrote them, courts interpret them on their own terms rather than filling gaps with general contract law. That cuts both ways: the balance is deliberate, and when you break a formal rule the courts enforce that too.

Outside Sweden, the nearest equivalent is a JCT or NEC suite in the UK, or NZS 3910 in New Zealand: standard general conditions attached by reference to a short contract. The Swedish versions are stricter about written notice, and they are not free to download — they are sold by Svensk Byggtjänst, which is why so many subcontractors have never read the terms they signed under.

DocumentUsed forWho carries the designTypical signer
AB 04Utförandeentreprenad (build-only)The client. You build to their drawings and specification.Main contractor to client
ABT 06Totalentreprenad (design-and-build)You. You owe a working function, not just workmanship.Main contractor to client
AB-U 07Subcontract under an AB 04 main contractFollows the main contractYou, to the main contractor
ABT-U 07Subcontract under an ABT 06 main contractFollows the main contractYou, to the main contractor

Utförande vs totalentreprenad: the line that decides your risk

Where small firms get hurt: a contract headed "AB 04" that hands you a performance requirement. Once you owe a result rather than a build, you carry ABT-style function liability inside a build-only contract, usually without the insurance to match. Check your cover includes design liability before you accept a single functional requirement.

The order of precedence — why the cover letter beats AB 04

AB 04 kap 1 § 3 ranks the contract documents. Changes to AB 04 rank above AB 04 itself, and the client's administrative specification (administrativa föreskrifter, "AF") ranks above the standard terms. The balanced document you were reassured about can be rewritten by two lines in the AF. The pack's own rule is that departures must be clearly listed as departures; in practice they are buried. Before signing, search the AF for the words that move risk: vite, garanti, betalning, säkerhet, and avsteg or ändring av AB 04.

ÄTA: the notice deadlines that forfeit the claim

ÄTA is ändrings-, tilläggs- och avgångsarbete: variations, extras and omissions. This is where small firms lose real money, and almost never because the work was disputed. It is form.

Two kinds of ÄTA

Half a prisbasbelopp moves every year. The prisbasbelopp for 2026 is SEK 59,200, so the threshold is roughly SEK 29,600. It is set annually by the government on SCB's calculation — look it up rather than reusing last year's figure.

The sanction is blunt. AB 04 kap 2 § 8 removes your right to payment where prescribed ÄTA was done without a written order, or likställd ÄTA without obtaining the client's view. You did the work, you built it well, you get nothing. Case law has softened the edges of the writing requirement, but a small firm should not plan to fund that argument.

The workflow that survives a dispute

  1. Something differs from the documents. Stop and photograph it from the angle that shows the discrepancy.
  2. Same day, send a written notice: what deviates, from which document, your price estimate, the time impact.
  3. Ask for a written order and say you are not proceeding without one. If they order verbally on site, confirm it in writing before you leave.
  4. Invoice it as a line item referenced to the order, never swallowed into a "final adjustment".

"Without delay" is not "at the monthly meeting". If your notices are dated three weeks after the photos, you are the one explaining. Letting the person on site log the deviation with a photo and a timestamp as it happens beats a good argument later. In OdinTask that is the job card the technician already has open, and the ÄTA carries through to the invoice — the point being that a notice you never billed is a notice you wasted.

Vite: delay is priced by the week

Under AB 04 kap 5 § 3 you pay vite for each started week you exceed the contract time or an adjusted completion date. The rate is not in AB 04 — the parties fill it in, and market rates commonly sit around 0.5–2% of the contract sum per week, sometimes capped at a number of weeks. Two things to check:

Your defence against vite is the extension of time, and it has its own notice duty: you claim time under the hinder provisions in kap 4, and you must notify the hindrance without delay or risk losing the extension. "Started week" matters — one day past Friday costs a whole week, so forcing to Friday is sometimes cheaper than "we're nearly there".

Garantitid vs ansvarstid: five years, then ten

Two different things, confused constantly.

After garantitid runs out but inside the ten years, the burden flips (kap 5 § 6): the client must show a material defect (väsentligt fel) caused by your negligence. That is a much higher bar than "it broke", so the years 5–10 tail is real but narrow. Your egenkontroll, photos and commissioning records are what decide these cases years after the van has left. Keep them in the job record, not on a phone that gets replaced.

The six-month rule almost nobody applies

AB 04 kap 6 § 19 gives you roughly six months from approval of the works to raise claims in writing, with a two-year period for claims concerning the contract sum itself. Late claim, no claim. Small firms lose ÄTA money here routinely: the site finishes, the folder goes in the cab, and eight months later someone tots up what was never invoiced. Put a calendar entry five months after every approved final inspection headed "any unbilled ÄTA on this job?". That one habit pays for itself.

Standard construction contracts: the clauses to query before you sign

  1. "AB 04 applies with the amendments in the AF." Ask for the amendment list as a document. If they will not produce one, the amendments are the contract.
  2. Vite base and cap. Tie it to your contract sum and cap it; a cap around 10% of your sum is a normal ask.
  3. Payment terms and retention. Longer than 30 days, or retention held past approval, needs a price attached.
  4. Pay-when-paid. You are not the main contractor's financier. Query any clause conditioning your payment on the client paying them.
  5. Extended garanti. A ten-year garanti gets slipped in. Your insurance almost certainly stops before that.
  6. Functional requirements in an AB 04 job. Either they go, or you are paid for ABT risk.
  7. Who can order ÄTA. Get a named person with authority in writing. "The site manager said so" is worth little if the site manager could not order.
  8. Dispute forum. Under kap 9 § 1 disputes go to the ordinary courts unless the value clearly exceeds 150 prisbasbelopp (roughly SEK 8.9 million at 2026 levels), above which it is arbitration. Arbitration is confidential and quick and can cost more than the claim. A clause forcing arbitration regardless of value prices you out of ever suing.

What is changing: AB 25 / ABPU 25

BKK is replacing the pack: AB 25 is intended to replace AB 04, and ABPU 25 to replace ABT 06. The drafts went out for consultation between October 2024 and February 2025 and drew roughly 4,000 responses from around 200 respondents. Publication has slipped — signals from BKK point to launch no earlier than 2026 and possibly 2027, and the names may change with the year. The drafts restructure the chapters, rework the ÄTA concept, firm up duties of loyalty and communication, and assume digital, model-based working.

None of which helps you this week. AB 04 and ABT 06 will be attached to contracts for years after any new pack lands, because projects run on the terms they were signed under. Learn the current pack.

The honest summary

These contracts punish bad admin far more often than bad work. Every rule above with teeth — the written ÄTA order, the notice without delay, the hindrance notice, the six-month window — is a paperwork rule. The firms that get paid are not the ones with the best lawyer; they are the ones whose site notes are dated, photographed and sent the same day. If your ÄTA notices live in text messages and your egenkontroll lives in a glovebox, close that gap first: try OdinTask free for 14 days, or see pricing. And when a contract lands with amendments you do not understand, an hour with a construction lawyer before signing is cheaper than any number on this page.

General information, not legal advice on your contract. The authoritative texts are AB 04, ABT 06 and AB-U 07 themselves, published by BKK and sold through Svensk Byggtjänst.

FAQ

What is the difference between AB 04 and ABT 06?

AB 04 covers utförandeentreprenad — build-only work where the client owns the design and you are liable for building it correctly. ABT 06 covers totalentreprenad — design-and-build, where you produce the solution and are liable for the function working, not just the workmanship. Under ABT 06 you cannot defend a defect by saying you followed the drawing, because the drawing was yours. Check your liability insurance covers design before accepting ABT 06 terms.

What is AB-U 07 and why does it matter to a subcontractor?

AB-U 07 is the subcontract companion to AB 04. It applies AB 04 in your relationship with the main contractor, with the additions and changes AB-U 07 makes, so the main contractor's obligations on time, quality and penalties flow down to you. ABT-U 07 does the same job under an ABT 06 main contract. It is normally attached by reference in a one-page order, which is why so few subcontractors have read it.

How quickly must I notify an ÄTA under AB 04?

Ordered variations (föreskriven ÄTA) should be ordered in writing before you start, under kap 2 § 6. For likställd ÄTA — where site conditions differ from the documents — kap 2 § 7 requires you to notify the client without delay, and to notify and obtain their position before starting if the work is estimated above half a prisbasbelopp (about SEK 29,600 in 2026). Miss it and kap 2 § 8 can remove your right to payment entirely.

How long is the garantitid under AB 04, and how does ansvarstid differ?

Garantitid is five years for the works from approved final inspection, with a shorter two-year period tied to products the client prescribed. Ansvarstid is ten years from approval and contains the garantitid. During garantitid, defects that appear are presumed to be yours. After it, inside the ten years, the client must prove a material defect caused by your negligence, which is a much harder case for them to make.

How much is vite for delay under AB 04?

AB 04 kap 5 § 3 makes vite payable for each started week you exceed the contract time, but the rate is blank in the standard text — the parties fill it in. Market rates commonly sit around 0.5 to 2 percent of the contract sum per week. Check two things: that it is calculated on your contract sum rather than the main contract sum, and that it is capped. Normally vite replaces other delay damages.

How long do I have to claim unpaid ÄTA money?

Under AB 04 kap 6 § 19 you generally have six months from approval of the works to raise claims in writing, with a two-year period for claims concerning the contract sum itself. After that the claim is time-barred, however good it was. Set a reminder five months after every approved final inspection to check for unbilled ÄTA — this is one of the most common ways small firms quietly lose money.

One system for your field-service business

Booking, quotes with ROT, scheduling, an offline app, time tracking and invoicing — in your own brand.

Try OdinTask free